Liquid Phase Heat Transfer System
Cleaning and Fluid Startup Procedure
Objectives:
1) Remove the used heat transfer fluid from the
system.
2) Solvate sludge and other degradation products as
much as possible for removal by draining.
FLUSHING FLUID
Radco offers a 100 SUS oil (XCELTHERM®
LT) that is additive-free and has a high
aromatic content for "hot oil" systems or an
aromatic solvent (XCELTHERM®
FF) for synthetic fluid systems. The higher
the aromatic content the better since it is the
aromatic component of the oil that has a solvent
effect on system sludge and other degradation
products.
PROCEDURE
1) Drain system including any obvious low points
such as the bottom of jackets, etc.
2) Break the lines at the pump intake and discharge.
Air blow the system to remove any "heel".
3) Charge the system with flushing fluid and
circulate at approximately 400 F° for approximately
8 hours. If system design permits, the flushing
fluid should be run through the expansion tank for
approximately two hours of this eight-hour period.
The volume of flushing fluid should be sufficient to
insure that the pump does not cavitate on start-up.
Although this volume is ultimately determined by
system configuration, a good rule of thumb is that
the flushing fluid volume should be approximately 80
% of the system fluid volume.
4) Again drain system including any obvious low
points.
5) Again break the lines at the pump and air blow.
6) Charge XCELTHERM® fluid, preferably from a system
low point to avoid airlocks, and follow start-up
procedures.
Radco
INDUSTRIES
www.XCELTHERM.com
LIQUID PHASE HEAT TRANSFER
SYSTEM
START-UP PROCEDURE
Objective: Vent any moisture which may have
condensed in the system and any residual light ends
remaining from a system flush.
PROCEDURE
In this procedure the fluid should be run through
the expansion tank if possible, as the lights will
be vented more quickly. In any event, a watch should
be maintained on the expansion tank vent or the
system pressure gauge. It is not unusual to see
puffs of vapor from this vent or an increase in
system pressure as the fluid is heated and the
lights escape. However, if an increase in the rate
of vapor generation is observed, the temperature
should be maintained or even slightly reduced until
the rate of venting lessens. Only then should the
temperature be increased.
1) At a temperature rate increase not to exceed 1°F
(½°C) per minute bring the system temperature to
200°F (93°C) and circulate for approximately the
length of time necessary for the heat transfer fluid
(HTF) to cycle once through the system. For example,
if the pump output is 180 gallons/minute (680
Liters/minute) and the system fluid volume is 1800
gallons (6800 Liters), the HTF cycle time is 10
minutes.
2) At the above temperature rate bring the system to
230°F (110°C) and circulate for 1 HTF cycle while
observing the expansion tank vent/pressure gauge.
3) At the above temperature rate bring the system to
260°F (127°C) and circulate for 1 HTF cycle while
observing the expansion tank vent/pressure gauge.
4) At the above temperature rate bring the system to
300°F (149°C) and circulate for 1 HTF cycle while
observing the expansion tank/pressure gauge. At this
point, if everything is running satisfactorily and
you have been running through the tank, the
expansion tank may be bypassed and the system put in
its normal fluid flow configuration.
5) The system temperature may now be raised to
operating temperature in 50°F (25°C) increments with
each incremental rise followed by an HTF cycle time
observation period.